Feb 14, 2019 Update

The activity next week will remain similar the previous weeks. Excavation will continue 24 hours a day on the First Street site and we will continue preparing the foundation of the Mission Street site. Mitchell Engineering will continue site utility work for the Oceanwide Center development. The work includes the installation of storm drain laterals […]