Happy Thanksgiving from the Oceanwide Center project! Our work site will have very light activity over the coming holiday weekend. Excavation on the First Street site is progressing and will continue over the next several months. We have completed our pedestrian safety improvements on both First Street and Mission Street along the site to provide overhead protection in advance of our vertical construction activities.

A&B Construction will be continuing their night work on the corner of Second Street and Mission Street for the new PG&E service to the project. This work is expected to be completed by mid-December. Please do not hesitate to reach out should you have questions.