May 5, 2017 Update

Later this week, Jessie Street between Ecker and 1st will be closed to cars and pedestrians as we begin the first phase of the Jessie Street reroute. Through traffic will be rerouted down Ecker Street to Mission.

Demolition at 50 1st will continue weekdays from 7:00 am – 4:30 pm and Saturdays from 8:00 am – 4:30 pm. This work is expected to be complete by early June.

PG&E will be working on 1st street near Jessie tomorrow evening until midnight. They will be removing equipment that is no longer in use.

Starting on May 19th for four weeks, steel will be delivered to the Mission Street site from the hours of Midnight-6am as Oceanwide begins the installation of the perimeter shoring wall. The City requires these deliveries to take place at night due to the large size of the steel piles, but every effort will be made to minimize the impacts associated with this work.

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *