Mar 12, 2018 Update

Neighbors should expect to see a downturn in construction activity on the 1st Street site over the next 7-10 days. While Oceanwide’s contractors will continue to be permitted to work 24 hours a day, the level of activity will be reduced significantly compared to the last several weeks. Towards the end of March, activity will pick up again as we continue work on the perimeter shoring wall.

By mid-next week, installation of the net protection over Ecker between Jessie and Mission will be complete. This portion of Ecker will remain open to vehicles and pedestrians during the installation of the netting.

Should you have any questions or concerns, please call the 24-Hour hotline at (415) 746-9948.