June 8, 2017 Update

On June 13 and 14, Ecker Street between Jessie and Mission Streets will be closed to install a vehicle safety barrier. This barrier will remain in place for the duration of construction. We will have flagging personnel at Anthony and Jessie Streets to assist with any delivery vehicles that need to access Jessie Street.

Demolition of buildings 40 and 50 1st Street is complete. Demolition work on the west side of 78 First Street will continue for the next several months.

Starting in Mid-June and continuing through November, drilled pile work will be performed 24 hours a day as we begin the installation of the deep foundations on the Mission Street site. We apologize for any inconvenience caused by this work. Unfortunately, there is no way to avoid this work as it requires that rebar and concrete be set immediately after shafts are drilled down to bedrock. We will do our best to limit impacts.

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *