Jan 13, 2017 Update

Beginning this weekend, Oceanwide or its authorized contractors will begin work on the southern portion of Ecker street between Mission and Jessie. This work includes planned pedestrian improvements and safety upgrades. Jessie street will continue to be closed during construction hours for the next 4-6 weeks.

Beginning January 16th and continuing for a period of three weeks, drilled pile work will be performed 24 hours a day. We apologize for any inconvenience caused by night work.  Unfortunately, there is no way around this as our tests require that rebar and concrete be set immediately after these test shafts are drilled down to bedrock. We will do our best to limit impacts.

Please note our 24 Hour Construction Hotline to be used in emergencies. 415.746.9948.