Jan 10, 2019 Update

Happy New Year! We have completed the excavation on the Mission Street site and are preparing the site for foundation work. We expect large concrete pours for our foundation to begin in March. Excavation on the First Street site is progressing and will continue over the next several months. We will continue to operate on site 24 hours per day during this time.

PG&E has completed their night work on the corner of Second Street and Mission Street. Our next planned night work will be for utility connections along First Street and we will provide you with a more detailed schedule in the coming weeks.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948