Feb 22, 2018 Update

Beginning this weekend and continuing next weekend, (2/24-2/25, 3/3-3/4), we will be installing overhead pedestrian and vehicular protection on Ecker between Jessie and Mission Street next to the work site. This will require the full closure of Ecker to vehicular traffic for both weekends from 7:00 am – 5:00 pm. Ecker will continue to remain open to pedestrians at all times.

The installation of our deep foundation will continue to be a 24-hour a day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock.