Dec 7, 2018 Update

We have completed our pedestrian safety improvements on First Street and Mission Street adjacent to Oceanwide’s site. These improvements provide overhead protection as vertical construction activities begin. We have completed the excavation on the Mission Street site and are preparing the site for foundation work.  We expect large concrete pours for our foundation to begin in February. Excavation on the First Street site is progressing and will continue over the next several months.

PG&E has completed their night work on the corner of Second Street and Mission Street. Our next planned night work will be for utility connections along First Street and we will provide you with a more detailed schedule in the coming weeks.

Please do not hesitate to reach out should you have questions.

Emergency Contact:

Swinerton | Webcor Joint Venture

24-Hour hotline at (415) 746-9948