Entries by jackblanchat

Jan 8, 2018 Update

Oceanwide’s contractors will continue drilled pile work at the 1st Street site. This will continue to be a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. We will continue our best efforts to limit the impacts of this work on the neighborhood, […]

Dec 21, 2017 Update

Happy Holidays!  Oceanwide’s contractors will not be working the evening of December 23rd through the morning of December 26th and the evening of December 29th through the morning of January 2nd. Oceanwide’s contractors will continue drilled pile work at the 1st Street site. Unfortunately, this will continue to be a 24-hour-a-day operation as the type of […]

Nov 29, 2017 Update

Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site immediately east of 1 Ecker along Stevenson Street. This work requires large steel beams to be delivered to the site for the next several weeks.  The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight […]

Nov 17, 2017 Update

The temporary overhead pedestrian safety protection will remain in place on the south side of Stevenson for the next week. Oceanwide’s contractors will continue installation of the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work requires large steel beams to be delivered to the site for the next […]

Oct 27, 2017 Update

The temporary overhead pedestrian safety protection has been installed on the south side of Stevenson. We expect that it will remain there for the next several weeks. Last week’s update noted that work would begin on the perimeter shoring wall this past Monday. Oceanwide had additional prep work to complete and this work did not […]

Oct 19, 2017 Update

Next week, Oceanwide’s contractors will begin installing the perimeter shoring wall on the First Street site immediately east of 1 Ecker. This work will require large steel beams to be delivered to the site for the next several weeks. The San Francisco Municipal Transit Agency (SFMTA) requires that all oversized deliveries occur between midnight and […]

Aug 28, 2017 Update

Oceanwide or its designated contractors will continue prep work for backfilling soil against the basement wall on the east side of One Ecker. The prep work protects the recently installed waterproofing and the structural integrity of the basement wall. Protection and backfilling will continue during daytime work hours for the rest of the month. We […]

July 14, 2017 Update

Continuing until late fall, Oceanwide’s contractors will be installing foundation piles for the Mission Street Tower. This work will require some additional night work. Unfortunately, this is a 24-hour-a-day operation as the type of foundation that is being installed requires that rebar and concrete be set immediately after these shafts are drilled down to bedrock. […]

July 7, 2017 Update

We hope you had a happy and safe 4th of July! Beginning in early July and continuing until late fall, Oceanwide’s contractors will be installing foundation piles for the Mission Street Tower. This work will require some additional night work. Unfortunately, this is a 24-hour-a-day operation as the type of foundation that we are installing […]

June 29, 2017 Update

Beginning in early July and continuing until late fall, Oceanwide’s contractors will be installing drilled foundation piles along the Mission Street site 24 hours a day. The foundation piles go all the way into bedrock, and the process of drilling and pouring concrete must be done in a 24-hour cycle and requires working at night. […]