Apr 6, 2017 Update

This Saturday, Oceanwide’s contractors will be working at 50 1st Street from 7:00 am – 4:30 pm. Continuing for the rest of the week and similar to last week, the hours of this work will be expanded from 7:00 am – 8:00 pm.

Mobilization will continue on the Mission Street site to prepare for the shoring of existing utility vaults adjacent to the site. This will include setting up concrete pumps and mobilizing additional crane and drill equipment. Oceanwide’s contractors have begun assembling test panels on site for the upcoming shoring work.

Please note our 24 Hour Construction Hotline to be used in emergencies: 415.746.9948.