Mar 31, 2017 Update

We are excited to announce that buildings 40 and 50 have been demolished to the ground floor level and there will be no further overhead demolition work.  Thank you for your patience as we reached this significant milestone in the project.

This Saturday, Oceanwide’s contractors will be working at 50 1st Street from 7:00 am – 4:30 pm.  Beginning Monday and continuing for the rest of the week, the hours of this work will be extended from 7:00 am – 8:00 pm.

Mobilization will begin on the Mission Street site to prepare for the shoring of existing utility vaults adjacent to the site. This work will include setting up concrete pumps and mobilizing additional crane and drill equipment. Starting the week of April 3rd, Oceanwide’s contractors will begin assembling test panels on site for the upcoming shoring work anticipated to start in the near future.

The project’s 24-hour construction hotline can be reached at 415-746-9948 if you have any concerns.

Mar 9, 2017 Update

This Saturday, Oceanwide’s contractors will continue internal demolition work on 50 1st street. The work hours are 8:00 am – 4:30 pm on Saturday.

Over the next two weeks, Oceanwide’s contractors will continue the demolition of 50 1st street and begin to prepare the site along Mission Street. This work will take place during regular work hours and will include mobilizing equipment for future work.

Jessie Street between Ecker and First Street will be closed daily from 7 a.m.-5 p.m. to ensure everyone’s safety during demolition.

Please call the 24-hour construction hotline 415-746-9948 if you have any concerns.